East Ranch Community Park Public Restroom Building Installation Project

Posted – Sept 12, 2024, Closes - October 4, 2024

The Cambria Community Services District is requesting formal, sealed bids from licensed contractors for the installation of a prefabricated restroom building, associated building utilities, and a concrete walkway. 

9/20/2024: Addendum Number 1 to the Bid Documents for the installation of a prefabricated restroom building, associated building utilities, and a concrete walkway are posted below.

The full request package can be accessed below.

Notice to BiddersPublic Works ContractExhibit A - Bid Proposal FormExhibit B - Project DescriptionExhibit C - Construction Mitigation MeasuresExhibit D - Stamped PlansExhibit E - Soils ReportExhibit F - Soils Review Letter

Addendum(s)

Any addendums will be added here during the open period of this RFP. Please sign and submit with the Bid Proposal Form any addendums that are added.

Addendum Number 1 to the Bid Documents

Submittal Procedures and Deadline

Formal Bids will be received until October 4, 2024, at 10:00 am.

Bids are to be delivered sealed to the District’s Wastewater Treatment Plant, located at 5500 Heath Ln, Cambria, CA 93428, or mailed to Cambria Community Services District (CCSD) P.O. Box 65, Cambria, CA. 93428 by October 4, 2024, at 10:00 a.m. At 10:30 a.m. at 5500 Heath Ln, Cambria, CA 93428, said formal bids will be opened. Emailed bids will be accepted at engineering@cambriacsd.org. Any bids which are delivered after this date and time will be refused. Any mailed bids received after this date and time will be returned unopened. Proposals that do not meet all the standards and requirements will not be considered.

Inquiries regarding this formal RFP should be directed to the Utility Manager via the Request for Information form on this page

Anticipated Schedule

MilestoneDate
RFP Issued9/12/2024
Recommended Pre-Bid Meeting9/30/2024
Deadline for Clarifications/Inquiries10/2/2024
Deadline to Submit Proposals10/4/2024
CCSD Selection of Contractor 10/10/2024
Contract Negotiations10/10/2024 - 10/17/2024
Notice to Proceed10/21/2024
Construction Start Date, Phase 110/23/2024
Construction Completion Deadline, Phase 111/19/2024
Construction Start Date, Phase 21/28/2025
Construction Completion Deadline, Phase 22/28/2025

*Weather permitting.

**Anticipated.

Bid Results