Zone 2 to Zone 7 Santa Rosa Bridge Water Line Replacement Project

Posted - June 1, 2021, Closed - June 15, 2021

The Cambria Community Services District is requesting quotes from licensed contractors for installation of a new 12-inch ductile iron pipe across existing steel bridge; tie-in to existing water lines; removal of tree; and replacement of south concrete approach. The completed project shall result in a fully functional permanent water line.

The full request package can be accessed below.

Informal Bid Package No 11-2021-06 Notice Inviting BidsExhibit A - Bid Proposal FormExhibit B - Project DescriptionExhibit C - Measures to Protect WildlifeExhibit D - SpecificationsExhibit E - Drawings

Addendum Number 1

Please sign and submit with the Bid Proposal Form

Addendum No. 1 (11-2021-06)

Submittal Procedures and Deadline

Informal Bids will be received until June 15, 2021 at 3:00 pm.

Bids are to be delivered to the District’s Utilities Department Office, 5500 Heath Lane, Cambria, CA 93428 until June 15, 2021 at 3:00 pm at which time and place said informal bids will be opened. Emailed bids will be accepted at engineering@cambriacsd.org.

A recommended pre-bid meeting is scheduled for June 8, 2021 at 10:00am at the Project Site.

Informal bid packages are to be submitted to:

Ray Dienzo, Utilities Department Manager/District Engineer
Cambria Community Services District
5500 Heath Lane
Cambria, CA 93428

Anticipated Schedule

MilestoneDate
RFP Issued6/1/2021
Recommended Pre-Bid Meeting6/8/2021
Deadline for Clarifications/Inquiries6/8/2021
Deadline to Submit Proposals6/15/2021
CCSD Selection of Consultant Team6/15-18/2021
Contract Negotiations6/21-25/2021
Notice to Proceed6/28/2021
Construction Completion Deadline*8/15/2021

 *Due to permitting constraints in the sensitive creek bed, all construction activities must be completed by August 15, 2021.